Gravity manure removal

Pens, feed dispensers and slatted flooring in an empty room at Ukrainska Volnytsia
Pens, feed dispensers and slatted floor, Ukrainska Volnytsia

A gravity system takes manure from under the slatted floor through channels and pipes to the lagoon.

It is built into the building design: gradients, levels and pipe diameters are set before any concrete is poured.

In a pig complex

We tie the manure network to the layout of the whole complex, from rooms to the lagoon.

Schematic, not to scale.

How it works

A wrong gradient or level is hard and expensive to fix after concreting.

That is why channels, pipes and connection points are designed together with the room layout, floors and ventilation.

An empty pig housing room at Ukrainska Volnytsia with pens, feed dispensers and slatted flooring
Slatted floor and pens in an empty room, Ukrainska Volnytsia

What it is made of

  • Underfloor channelsManure collects under the slatted floor of each room.
  • PipeworkPipes from rooms to the external network and the lagoon.
  • Gradients and levelsProcess gradients that keep the flow moving by gravity.
  • Link to floors and ventilationChannels are designed together with slatted floors and air exchange.

Where we have done it

The sites where we built this system, with photos from each.

What the calculation needs

If the data is sufficient, a preliminary calculation is possible before a site visit.

  • Site master plan and lagoon position
  • Room layout and floor type
  • Ground levels of the site, if available

A calculation for your building

Send the building size, the stock and the task. The topic “Gravity manure removal” will already be in the form.

The Ukrainska Volnytsia site in winter with production buildings, a feed bin and vehicles

What suits you best?

Preliminary calculation +380 67 509 47 33 office@farmer.com.ua

You receive a preliminary budget, a specification and a sketch, usually in two options or one with extras.